projects:biological_waste_treatment [2025/03/16 21:28] equinnprojects:biological_waste_treatment [2025/03/17 13:13] (current) equinn
Line 8: Line 8:
  
 ==== Cost breakdown ==== ==== Cost breakdown ====
-The figures below include VAT (27 %).+The figures below include VAT (27 %). This was calculated on: 2025-03-17
  
   * Main tank: 1080000   * Main tank: 1080000
Line 18: Line 18:
  
 ==== Existing piping/cabling underground ==== ==== Existing piping/cabling underground ====
-{{:projects:cimg5254.jpg?200|}}+{{:projects:cimg5254.jpg?200|}}{{:projects:cimg2244.jpg?200|}}
projects/biological_waste_treatment.1742160523.txt.gz · Last modified: 2025/03/16 21:28 by equinn