 ==== Cost breakdown ==== ==== Cost breakdown ====
-The figures below include VAT (27 %).+The figures below include VAT (27 %). This was calculated on: 2025-03-17
  
   * Main tank: 1080000   * Main tank: 1080000
Line 16: Line 16:
   * Installation: 381000   * Installation: 381000
   * Complete system: approx. 2300000   * Complete system: approx. 2300000
 +
 +==== Existing piping/cabling underground ====
 +{{:projects:cimg5254.jpg?200|}}{{:projects:cimg2244.jpg?200|}}